Getting Electricity / Water Connection


This service helps the customers to obtain power / water connections to their various projects. Application for getting electricity / water can be submitted through the E-Services ‘One Window’ system, by accessing this service using the user ID & Password. 

Customer shall fill the details, given in the application as applicable, and upload the technical documents and details as listed in the application. The documents will be technically reviewed for approval and preparation of DEWA Estimate / Connection Charges and processed further for field inspection, etc.

The Estimate / Connection Charges will be forwarded for payment after which DEWA’s field works will be executed. The customer will be able to track the status of the application, upload additional documents, download the approved documents, project status notification for the technical inspection, etc. through one window system.  


**Refer AL NAMOOS Services for up to 150kW permanent new electricity connections.

Fees: 

Application for service is free of charge. Service is chargeable (where applicable).

Delivery Duration:

LV Design Approval:

• Load from 1‐150 kw: 1 working day
• Load from 151‐400 kw: 2 working days
• Load from 401‐5000 kw: 7 working days
• Load from 5001 and above: 12 working days

Issuance of Connection Cost:

• Load from 1 to 150 Kw: 1 working day
• Load from 151 to 400 Kw: 4 working days
• Load from above 400 Kw: 8 working days

LV Inspection:

• Load from 1 – 150 Kw: 1 working days from the date preferred by the authorized electrical Contractor for the project

• Load from above 150 Kw: 2 working days from the date preferred by the authorized electrical Contractor for the project


HV Substation Location & size Approval (If any)

• 4 working days

HV Substation Inspection (If any)

• 1 working day from the date preferred by the authorized electrical Contractor for the project


Online Guide

Online Application Submission

Fill-in the online application form with required information attach necessary documents listed below, then submit the form. On successful submission, a reference number will be provided:

Mandatory Documents for Water Connection :

- Types of Connections: 

  1. Single:  Premises that include a single meter (i.e. villa, hotel building… etc.). 
  2. Multi: Premises containing more than one meter within the same property (i.e. building apartment). 
  3. Development: Housing communities that have more than one meter within the area (i.e. Emaar Developments, DAMAC… etc.).


- The following documents are required:

  • Building Permit/NOC
  • Proposed location of meters and sub-meters
  • Layout Drawing (i.e. floor plan indicating plumbing system)
  • Water storage tank details (i.e. drawing inlet level, capacity, location)
  • Green Building Regulation Implementation Documents (.pdf format only)
  • Premise Details Sheet (.xls/.doc format)
  • Meters Requirements Details (.xls/.doc Format)
  • Total calculation for water consumption, as per building code and accommodation

Mandatory Documents for Electricity Connection :

  • Total Connected load/Max. Demand schedule (.pdf Format)
  • MDBs/SMDBs Schedules (.pdf Format only )
  • Single Line Diagram with proposed LV distribution and tariff metering (.dwf Format)
  • Site setting lay-out and ground floor plan indicating location of substation, LV room (along with dimensional details of LV room, arrangements of LV Panels, MDBs, KW  metersetc..) (.dwf Format)
  • Ground floor and/or typical floor plan indicating location of Electrical rooms/MDBs/SMDBs etc (.dwf Format)
  • General arrangements of KWh meters in ground and/or typical floor electrical rooms (.dwf Format)
  • Typical Load distribution schedule for final distribution board. (.pdf Format )
  • Affection Plan+Passport copy/Trade License copy (.pdf Format)

Optional Documents for Electricity Connection:

  • Green Building Regulation implementation documents. ( .pdf Format only)
  • Technical specification of Chiller/Motor loads and other documents. (.pdf Format )
  • Premise details sheet ( .xls/.doc Format )
  • Material requirements details ( .xls/.doc Format)
  • Consultant confirmation letter(No wet area, above electrical room/DBs, Circuit breaker/circuit cables, UV relays, ELCBs etc) in DEWA's prescribed format (.pdf Format)
  • DM Approved Thermal Load Calculation sheet

Application Status Tracking and Notifications

Customer will receive SMS and e-mail notifications regarding the progress of the application (submission, revision, approval, etc.) In addition to notifications, the status of the application can also be tracked online through the tracking page of the e-service.

 Application Revision

Getting electricity application can be revised once the estimate is issued to the customer by using revision option.

Service Delivery 

Once the technical documents are approved, a notification will be sent through SMS or email, DEWA estimate will be issued to the customer and notification for further coordination for technical inspection requirements, etc., up to release of power/water connection will be sent through the web site.


contact us by phone

By Phone

contact us by email

By Email or Post

contact us by location

Video Conferencing System

Our country is blessed and so are we, living in this good land

Mohammed bin Rashid Smart Majlis

Mohammed bin Rashid Smart Majlis

Visit Website