Use the toggle below to switch the contrast
Listen to the content of the page by clicking play on ReadSpeaker.
To discover more about accessibility view our
This service helps the customers to obtain power / water connections to their various projects. Application for getting electricity / water can be submitted through the E-Services ‘One Window’ system, by accessing this service using the user ID & Password.
Customer shall fill the details, given in the application as applicable, and upload the technical documents and details as listed in the application. The documents will be technically reviewed for approval and preparation of DEWA Estimate / Connection Charges and processed further for field inspection, etc.
The Estimate / Connection Charges will be forwarded for payment after which DEWA’s field works will be executed. The customer will be able to track the status of the application, upload additional documents, download the approved documents, project status notification for the technical inspection, etc. through one window system.
**Refer AL NAMOOS Services for up to 150kW permanent new electricity connections.
Fees:
Application for service is free of charge. Service is chargeable (where applicable).
Delivery Duration:
LV Design Approval:
• Load from 1‐150 kw: 1 working day
• Load from 151‐400 kw: 2 working days
• Load from 401‐5000 kw: 3 working days
• Load from 5001 and above: 3 working days
Issuance of Connection Cost:
• Load from 1 to 150 Kw: 1 working day
• Load from 151 to 400 Kw: 3 working days
• Load from above 400 Kw: 3 working days
LV Inspection:
• Load from 1 – 150 Kw: 1 working days from the date preferred by the authorized electrical Contractor for the project
• Load from above 150 Kw: 2 working days from the date preferred by the authorized electrical Contractor for the project
HV Substation Location & size Approval (If any)
• 3 working days
HV Substation Inspection (If any)
• 1 working day from the date preferred by the authorized electrical Contractor for the project
Fees:
Application for service is free of charge.
Connection Fees:
As per daily water demand, required materials, Authorities approvals, and site condition.
Estimation release:
Water estimation will be released when all requirements are fulfilled by the applicant. (The Water estimation is valid for only one year from date of Water estimation release)
Cost estimate for ½ & 1” direct meter connections will be released in 1 working day
Service Delivery:
- 5 working days from payment and the scheduled shutdown for Large meter connections.
- 3 working days from payment, building readiness, compliance with AMI requirements and the submission of all required documents for small meter connections.
Service Activation:
The water shall be release when all required payments are made if applicable (pending payments, security deposit, and pending bills)
Online Application Submission
Fill-in the online application form with required information attach necessary documents listed below, then submit the form. On successful submission, a reference number will be provided (Reference number for water application W-xxxxxx, reference number for Electricity application E-xxxxxx):
Water Connection:
Types of Connections:
Water Connections Categories:
Mandatory Documents for Water Connection:
Mandatory Documents for Electricity Connection :
Optional Documents for Electricity Connection:
Application Status Tracking and Notifications
Customer will receive SMS and e-mail notifications regarding the progress of the application (submission, revision, approval, etc.) In addition to notifications, the status of the application can also be tracked online through the tracking page of the e-service.
Application Revision
Getting electricity application can be revised once the estimate is issued to the customer by using revision option.
Service Delivery
Once the technical documents are approved, a notification will be sent through SMS or email, DEWA estimate will be issued to the customer and notification for further coordination for technical inspection requirements, etc., up to release of power/water connection will be sent through the web site.