Fitout Application

This service enables customers to obtain fitout power connection to shops and offices.

Fees:

Service is free of charge.

 Delivery Duration:

• Design Approval: 2 working days.

• LV Inspection: appointment will be given within 2 working days from readiness date notified by contractor.

Online Guide

Online Application Submission

Fill-in the online application form with required information attach necessary documents listed below,then submit. On successful submission, a reference number will be provided:

Mandatory Documents:

  • Copy of DEWA approved TCL/MD, MDBs/SMDBs etc... schedule (Main project)
  • Load distribution schedules of distribution boards.
  • Wiring Layouts – Lighting
  • Wiring Layouts – Power
  • Landlord NOC ( In DEWA prescribed format)
  • Tenancy Contract + Trade License + Passport Copy


Application Status Tracking and Notifications

Customer will receive SMS and e-mail notifications regarding the progress of the application (submission, approval, etc) In addition to notifications, the status of the application can also be tracked online through the tracking page of the e-service.

 

Service Delivery

Once the technical drawings are approved by DEWAm contractor can submit for technical field inspection. Subject to inspection approval, DEWA will arrange installation of KWh meter and release of power connection up on payment of Security Deposit. Notifications will be sent through the web site.



contact us by phone

By Phone

contact us by email

By Email or Post

contact us by location

Video Conferencing System

Our country is blessed and so are we, living in this good land

Mohammed bin Rashid Smart Majlis

Mohammed bin Rashid Smart Majlis

Visit Website