2) DEWA’s website: For projects within free zones and the jurisdiction of other licensing entities – such as Trakhees, the Dubai Development Authority, Dubai Integrated Economic Zones, etc – the NOC for construction electrical supply is processed within two working days while the NOC for construction water supply is processed within three working days after submission of the application.
Service Steps:
1. Apply for the NOC online and attach the required documents.
2. After submission, the applicant receives a confirmation notification containing the application reference number.
3. If the application is rejected, the applicant receives a notification to submit a new application containing valid or additional information.
4. If the application is returned with comments, the applicant receives notice to resubmit the application with the correct or additional information.
5. Upon approval of the application, the applicant receives a notification containing a link to download the NOC.
Details related to Building No-Objection Certificate – Electricity/Water and the journey map for project owners or contractors/consultants are available on DEWA’s website.