Requirements and Steps

Requirements and Steps

  • Apply online through DEWA’s website
  • Submit applications for both construction and permanent supply (together).
  • Payment should be made for construction and permanent supply services.
  • Install a meter cabinet for construction supply close to the permanent supply meter cabinet to avoid supply cable shortages.
  • Mechanical arrangements (if required) should be provided within the construction supply meter cabinet to facilitate the termination of the DEWA cable.
  • When construction is completed, DEWA will disconnect construction power supply after the first permanent supply inspection.
  • After disconnecting the construction supply, the contractor must re-terminate the cable into MCCB for permanent connection.